“It’s an impressive site, and it’s particularly pleasing that they have come this far with a very good health, safety and environment (HSE) record,” he says.
“The last time I was here there was not so much to see on the surface. But now you can picture what the Qatalum site will look like when it’s finished. I congratulate everyone involved in this tremendous effort and hope the rest of the project progresses equally successfully.”
15,000 construction workers
At the moment there are almost 15,000 workers on site, though peak manning is expected from December to March when there will be more activity than ever.
In the potroom buildings there is good progress on the foundations, while steel erection has started and is picking up speed. The paste plant, gas-power plant, office buildings and other buildings are all rising out of the sand, and construction of the jetty is well under way.
Challenging
“It’s a challenge to build such a large greenfield plant in the Gulf area these days. There are a lot of major investment projects, resulting in an overheated local civil and construction market with lack of skilled laborers and construction materials,” says Executive Vice President Tom Røtjer, head of Projects in Hydro.
“We are also keeping a close eye on the financial turmoil to see how it may affect our contractors. But let me add that our main challenge is really the sheer size of the project.”