Production resumed at Paragominas and Alunorte
Skip to content

On December 18, a transmission tower overturned, ceasing power supply to Paragominas, temporarily halting the production at the mine. The transmission tower has been repaired, and the power connection resumed.  

There were no personnel injuries, damages to other production assets or impact on the nearby environment related to the power outage.

Financial and operational impact has been limited, and no negative customer impact is expected.   