There is a license error on this site:
This license is for URL http://inte.hyal01mstred230.hyal.episerver.net/ but the current site has URL https://www.hydro.com/
The Web site remains functional, but this message will be displayed until the license error has been corrected.

To correct this error:If you do not have a license file, please request one from EPiServer License Center.
Production resumed at Paragominas and Alunorte
Skip to content

On December 18, a transmission tower overturned, ceasing power supply to Paragominas, temporarily halting the production at the mine. The transmission tower has been repaired, and the power connection resumed.  

There were no personnel injuries, damages to other production assets or impact on the nearby environment related to the power outage.

Financial and operational impact has been limited, and no negative customer impact is expected.   

Contacts

Recommandé pour vous

{{ abstract }}