There is a license error on this site:
This license is for URL http://inte.hyal01mstred230.hyal.episerver.net/ but the current site has URL https://www.hydro.com/
The Web site remains functional, but this message will be displayed until the license error has been corrected.

To correct this error:If you do not have a license file, please request one from EPiServer License Center.
Hydro issues force majeure notice due to production problems at MRN
Skip to content

MRN, where Hydro has a 5% ownership and additional 40% offtake, is experiencing problems with its tailing systems due to lack of water. The lack of water is caused by a very dry period in the region. This is expected to reduce production of bauxite from a previously expected level of 17-17.5 million mt to around 15-15.5 million mt in 2017.   

As the production shortfall is mostly related to dry bauxite for the export market, it is not expected that production at the Alunorte alumina refinery will be affected.

MRN has a nameplate capacity of around 18 million mt and is one of the world's largest bauxite mines. 

Raccomandato per te

{{ abstract }}