Hydro had scheduled the replacement of two sections of the pipeline in Q3 and Q4 2020, as part of the long-term maintenance plan for the pipeline.
During the planned maintenance work in Q3, it was discovered that a section of the pipeline had deteriorated faster than expected. Based on a technical assessment, it was decided today to extend the maintenance and replace this section of the pipeline earlier than initially scheduled.
The work will commence immediately, and operations are expected to resume within two months.
During this period, production at Alunorte will be reduced, expected to a level between 35-45 percent of full capacity, to balance bauxite inventories. The reduced production will impact the financial results for Q3 2020.
Hydro is taking all necessary measures to mitigate any customer impact.
Pubblicato: agosto 18, 2020